INTERNATIONAL CYBERNETICS CORPORATION
SurPRO 2000 DATA REPORT
International Roughness Index Bumps
-----------------------------------
Report Date: 22:40:32 2007/01/06
File Name: 08NO0023.PFL (File Loaded from Disk)
Profiler Configuration
----------------------------------------------------------------
Model/Serial #: 2000 33
Software Revision: V4.0.4.00 2007/01/04
Wheel/Step Dist (m): 0.2500 0.0200
Dist Cal (counts/m): 27105.96
Incl Bias Drg (mrad): 3.05012
Incl Bias Aft (mrad): 3.05012
Incline Bias How: Two Way Cal
Incline Bias Date: 12:47:50 2005/10/19
Incline Bias Temp (øC): 33.6
Incline Gain Value: 1.000000
Test Description
----------------------------------------------------------------
Route: I35
County: STORY
Operator: REOSR
Project Number: 1
Contractor: ICC
Other1: L G
Other2: 39IN TO EDGE
Dirn Data Collected: Forward
Direction (Compass): N
Lane: 1
Wheelpath: R
Test Data
----------------------------------------------------------------
Test Date:
Start Time:
End Time:
Velocity Avg (km/h): 2.419
Velocity Max (km/h): 2.793
Steps: 10050
Distance (m): 201.00
Start Elevation (m): 0.000
End Elevation (m): 0.000
Temperature (øC): 31.2
Total Events: 3
Operating Mode: Rolling
Report for Section 3, from 100.0 to 150.0 m
----------------------------------------------------------------
IRI Bump Analysis Parameters
----------------------------------------------------------------
Note 1: These are bumps found using 'Bump Strategy' from surmenus.txt
Note 2: 'B' is Bump, 'D' is Dip
Note 3: 'Length' is difference between 'Stn To' and 'Stn From'
Note 4: 'IRI Actual' is IRI after grinding bumps and filling dips
Note 5: 'IRI Target' is 'IRI Target' from surmenus.txt
Note 6: 'Max Grind' is 'Max Grind' from surmenus.txt
Note 7 +'ve Grind means remove material, -'ve Grind means fill with material
Note 8: Dips will be filled if 'Find Dips?' from surmenus.txt is 'Yes'
Note 9: Bumps/Bumps, Dips/Dips and Bumps/Dips are not permitted to overlap
Note 10: 'IRI Redctn' is the contribution to total IRI reduction by grinding
individual bump from 'Grind From' to 'Grind To', to 'Grind Depth'
User Bump Strategy: By Severity
IRI Actual (m/km): 0.976
IRI Target (m/km): 1.000
Max Grind (mm): 20.0
Find Dips? No
IRI Bumps Report
--------------------------------------------------------------------------------
Total Bumps = 2, sorted by 'Height'.
Count Stn Stn Stn Length Height Grind Grind Grind IRI
From To Max Max From To Depth Redctn
# m m m m mm m m mm m/km
--------------------------------------------------------------------------------
B 1 119.9 138.7 125.7 18.8 15.9 120.5 138.3 15.0 0.496
B 2 108.8 119.7 113.5 10.9 15.4 108.8 119.7 15.4 0.776
Bump Grinding Plan
--------------------------------------------------------------------------------
Grinding Strategy is: Grind Bumps to Reach Minimum Specification.
Grinder Full Depth (mm): 3.0
Minimum Grind Length (m): 2.0
Count Pass Stn Stn Stn Stn Grind
Start Start End End Length
Grind Full Full Grind Start
Depth Depth - End
# # m m m m m
--------------------------------------------------------
B 1 1 120.5 121.1 134.7 138.3 17.8
2 121.1 121.9 132.2 134.7 13.6
3 121.9 122.9 129.3 132.2 10.2
4 122.9 123.9 127.3 129.3 6.4
5 123.9 125.6 125.7 127.3 3.3
--------------------------------------------------------
B 2 1 108.8 110.7 118.5 119.7 10.9
2 110.7 111.4 117.2 118.5 7.9
3 111.4 111.8 115.7 117.2 5.8
4 111.8 112.2 114.4 115.7 3.9
5 112.2 113.3 113.7 114.4 2.1
*** End of Report ***
---------------------
|